PLATFORM WILL NOT RAISE, MOTOR RUNS
2. Try raising platform (activate UP
toggle switch). Only the motor
solenoid (FIG. 80-1) should be
energized while raising platform.
The “A”, “B”, “C” and “E” solenoid
valves (FIG. 80-1) (located in the
pump box) should not be energized.
Connect voltmeter to terminal-1 and
terminal-2 on each valve shown in
FIG. 80-1. Correct indication is 0
volts dc. If voltmeter indicates +11 to
+12.6 volts dc for any of the valves,
check control switch and wiring to the
valve (refer to ELECTRICAL SYSTEM
DIAGRAMS section). Replace faulty
wiring or control switch as required.
1. Check the hydraulic uid level in the reservoir.
“E” VALVE
(3-WAY)
VALVES & ELECTRICAL CONNECTIONS
FOR POWER DOWN PUMP
FIG. 80-1
MOTOR
SOLENOID
“C” VALVE
“B” VALVE
“A” VALVE
TYPICAL
TERMINAL-1
TYPICAL
TERMINAL-2
GRAVITY DOWN LIFTGATES: Lower the platform to the ground. Clean dirt and uid
from top of reservoir in pump box. Fill the reservoir to correct level indicated on sight
glass (pump box).
POWER DOWN LIFTGATES: Raise the platform to bed height. Fill the reservoir to
correct level indicated on sight glass (pump box).
NOTE: For dual pump system, check secondary pump and motor rst.
NOTE: Numbers for the electrical terminals shown in the illustration are
not stamped on valve coil. Numbers shown are for reference only.